HomeMy WebLinkAbout26 Long Hill RoadRUSSELL
O DAWSON
ARCHITECTURE
ENGINEERING 330 ROBERTS STREET (EXIT 58,1-84)EAST HARTFORD,CONNECTICUT 06108-3654 PHONE(860)289-1100 FAX(860)289-3272
July 28, 2003
John Collins, Bldg. Insp.
Town of South Windsor
1540 Sullivan Avenue
South Windsor, CT 06 74
f
Re: p tie
South Windsor, CT
File: 03.197
Dear Mr. Collins:
During the construction of a residence at the above lot, the footing/foundation was over-excavated
by 3 feet.
I have been informed that the condition of excavated material is satisfactory fora residential
foundation. The contractor asked for alternates to pouring the new footing at the lower elevation
which would require considerably more concrete. To accommodate the condition, the final floor
elevation will be adjusted 1 foot lower which will require approximately 2 feet of fill material in
the excavation.
Two inch diameter crushed stone shall be placed in the over-excavated portion up to final bottom
of footing elevation. The stone should be placed in approximately 8" layers, lightly tamped. This
will provide a satisfactory bearing condition for the building foundation.
The foundations will be structurally satisfactory with the above work.
Very truly yours,
a
a O
ONawac7_
son, III
Consulting Engineer
RMD/nla
Cc: Peter DeMallie,Design Professionals via fax and hand-delivery 291-8757
File: 03.197/072803L