June 17, 2011
CERTIFIED MAIL 70081300 00014578 3917
Patrick Gorman
160 West Street
Suite E
Cromwell CT 06416
Dear Mr. Gorman:
Re: Appl. 11-03P. Medical Office building
We are pleased to advise you that the Planning & Zoning Commission voted on June 14, 2011 to approve the
change order for minor modifications to the site plan and architectural elevations for the above mentioned
application.
This approval is subject to the following conditions as stated in the previous approval letter dated February 10,
2011.
1. Prior to commencement of any site work, a meeting must be held with Town Staff.
2. No building permit will be issued until the final mylars have been filed in the Town Clerk's office.
3. This application is subject to the conditions of approval of the Inland Wetlands Agency/Conservation
Commission,including bonds in the amount of$5,000 to ensure compliance with the erosion and sediment
control measures and$5,000 to ensure establishment of storm water system and$25,000 for the
construction of the wetlands mitigation.
4. A landscape bond in the amount of$5,000 is required and must be submitted prior to filing of mylars.
5. All bonds must be in one of the forms described in the enclosed Bond Policy.
6. An as-built plan is required prior to issuance of a Certificate of Occupancy per Article 9.1.2.13 of the Zoning
Regulations.
7. All plans used in the field by the developer must bear the stamp and authorized signature of the Town of
South Windsor.
8. This approval does not constitute approval of the sanitary sewer, which can only be granted by the Water
Pollution Control Authority.
9. The building street number must be included on the final plan.
10. Pavement markings must be maintained in good condition throughout the site drives and parking areas.