HomeMy WebLinkAboutApplication Files_85048_pg0031 Bubaris.§'Traffic James G.Bubaris PE.
' A S S O C A T E S Principal
PIanningeEngineeringo Des ign
January 10, 2011
' Mr. James Ussery, L.L.S.
Senior Project Manager _
' J.R. Russo &Associates, L.L.C. RECEIVED
1 Shoham Road
East Windsor, CT 06088
' JAN 9 2011
Re: Site Traffic Evaluation Study
Proposed Fed-Ex Distribution Center
s�UTHWiNDSORPlAt�11NGDEPT.
' Sullivan Avenue (CT Route 194) and Kennedy Road
South Windsor, Connecticut
Dear Mr. Ussery:
Reference is made to the proposal to develop a Fed-Ex Ground distribution
' center on the parcel of land located on the north side of Sullivan Avenue (CT
Route 194), east of Kennedy Road, in the Town of South Windsor,. Connecticut.
Please refer to Exhibit 1 of the Appendix which locates this site with respect to
' the surrounding roadway network.
' Introduction
The distribution cent ill-nifial sist of about 21,338 square feet f
' building area and 1 arking spaces s identified in Table on a next page
which summarizes the propose Fd-eve opment parameters. This partial build
scenario is expected to be operational by 2013. Access and egress for this
' development will be provided via Kennedy Road at its interface with Sul Ivan
Avenue. Ultimately, the full builds ri ill increase building area t 309,718
square feet and parking spaces t 1,084. he full build scenario is no
' to be in place until 2017. Please re xhibit 2 of the Appendix which provides
a copy of the site plan for the proposed development wherein the initial partial
development scenario is the subject of the pending application, analysis and
' review.
Section 13-311 of the Connecticut General Statutes stipulates that all
' developments that either abut or materially impact a State highway, and that
have development parameters that either exceed 100,000 square feet of building
area or 200 parking spaces, require the issuance of a Certificate of Operations
' from the State Traffic Commission (STC). The subject development directly
abuts a State highway, and even its initial-partial build"development parameters
exceed the minimum 100,000 square feet of building area and/or 200 parking
' spaces which cause it to require STC review and approval.