1540 SULLIVAN AVENUE • SOUTH WINDSOR, CT 06074
f�OSR.c° TELEPHONE(860) 644 2511
March 29, 2010 RECEIVED
Paul Vitaliano, P.E. MAR S ? 2010
Vanasse Hangen Brustlin, Inca son IVI(yQ,gpR RAW DW
54 Tuttle Place
Middletown, CT 06457
Re:Connecticut Studios—WPCA Approval
Dear Mr. Vitaliano:
The South Windsor Water Pollution Control Authority, at its special meeting of March 23, 2010, gave
approval to the application as presented for connection to the Town's sewerage system for a proposed
motion picture and television studio, production and post production facility located at R011A Chapel
Road, 245 Chapel Road, R008 John Fitch Blvd., and 240 Ellington Road, South Windsor, CT, as more
specifically shown on plans entitled "Connecticut Studios, South Windsor, Connecticut" Prepared by
Vanasse Hangen Brustlin, Inc., Providence, RI; Dated February 26, 2010, Project Number 72189.00;
Drawing Number C-10, Sheet 10 of 17,"Utility Plan, Panel 1"and Drawing Number C-11, Sheet 11 of 17,
"Utility Plan, Panel 2". This approval is subject to the following conditions:
1. Given the flatness of the site and the slope of the pipes, the Town Engineering Department shall
be provided with and shall approve the proposed sewer plan, based upon recalculated flow
velocities for the proposed sanitary sewer plan;
2. Include a stub on manhole no. 7 in order to have a transition point between the force main and
the gravity system;
3. Technical approval of the Town of South Windsor Engineering Department;
4. Payment'of a connection charge in the amount of $101,400.60 at time of connection for 29.4
acres; and
5. Final Authority approval and acceptance of the sanitary sewerage connection will be conditional
upon the sewer line having been installed and inspected by the Town staff, and upon the written
verification of the Town staff that said sanitary sewer line was installed in substantial
conformance with the design plans approved by the Authority, and meeting all Town regulations
and appropriate technical specifications relating to sanitary sewer construction.
This approval letter must be superimposed on the final approval plans.
Very truly yours,
Joseph J.Carino,Chairman
Water Pollution Control Authority
JC:ead
cc: Michael J. Gantick, Director of Public Works
)eff Doolittle, Town Engineer
i/Marcia Banach, Director of Planning
Chris Dougan, Chief Building Inspector