HomeMy WebLinkAboutWell Correspondence 00 Miller Road (3) MEMORANDUM To: Bob Deptula, Town Sanitarian From: Jerry C. Iazzetta, P.E., Town Engine Date: March 8, 2001 Re: Miller Road Water Main Extension A review of the preliminary design drawings for the Miller Road water main extension was made. The following are our comments: Details — Sheet 6 The"Typical Water Installation Detail"does not comply with the Town's Standards for a trench. The thickness of pavement and class of pavement is not shown (minimum 3" or match existing). Also, thickness of processed stone is not shown (minimum of 6') and the processed stone is to be placed over a minimum of 6"of gravel. Miscellaneous Details — Sheet 8 Temporary Pavement Repair, Permanent Pavement Repair (Town Road), Town Road Full Width Overlay (Alternate) and Mill and Overlay details do not meet the Town Standards. Title Sheet My name is not spelled correctly. Post-ItIm brand fax transmittal memo 7671 #of pages ► To-'ohn From` 1 () Co. Co. �j Dept. Phone# Fax# Fax# JCl/awp S:ENGINEER\Pro).—Construction\Miller Rd.Water Main Ext.\March 8 2001 comments Yw�_�r, .. !x"4°� tc.� J —�" ' "_ ---— ---- _ __ __ _ _ _----- .mod�._�� _. --���'z",� _ '_-------- _-- ---- ----- �-F--- --�—__ e,�'' ----------- ---- -----_--_ --- V� _ -- __- ___ --- -- - -_ -- -- --- wo � IA- . . . . . . . . . .._ . . lot Qw— • Fuss&O'Neill Inc. MEMORANDUM TO: Bob Deptula, South Windsor Environmental Health Officer FROM: Michael S. Anderson, P.E., Fuss & O'Neill"A RE: DEP's Required Construction Contract Provisions Barber Hill Road Water Main Extension DATE: February 15, 2001 As a follow up to our coordination meeting with Connecticut Water on December 8,2000,we have discussed some of the meeting's decisions with Mike Senyk. As you might expect, the DEP has some fairly rigid policies for bidding and construction of State funded projects. The following is our understanding of the DEP's policies which will change our approach to the referenced project: 1. Connecticut Water indicated that they would like to pre-approve bidders. The DEP has instructed us to make this a publicly open bid. We will include qualifications requirements in our bidding documents, and a review of the apparent low bidder's qualifications will be conducted before recommending an award. 2. Connecticut Water also indicated that they would inspect the water main and services as they are installed. However,the DEP would like the design engineer to inspect the work. The DEP noted the Connecticut Water may inspect the work on their own and offer advice where appropriate,but they shouldn't submit an invoice to the DEP for their inspection time. 3. The DEP would prefer to not have materials pre-purchased. The contractor should be responsible for purchase of all materials such as the meters. We recommend requiring that the contractor purchase the meters from Connecticut Water directly. In fact, we would like to list this cost in the bid documents. 4. For all materials that Connecticut Water needs to standardize on,we will need to submit a letter to the DEP to formally request authorization to bid these items as sole source,b including justification for this. r, Subsequent to our meeting, Jerry Iazzetta had asked us to use some of the Town's front end material in the bid package. The DEP will require that the bid package be arranged in their format as shown on the DEP's Plans and Specifications Checklist(attached). Please contact us if you have any questions about this material. We will proceed with completion of the plans and specifications'based on this information. We expect to submit review copies to the Town,DEP and Connecticut Water within 3 weeks. c: Michael Cunningham, Connecticut Water Mike Senyk, DEP G:\P2000\301\AIO\400\msaO2l4a.wpd Cones.(HQ) GRANTS TO MUNICIPALITIES FOR POTABLE WATER SUPPLIES PLANS AND SPECIFICATIONS CHECKLIST Applicant Contract Name&Number Consulting Engineer Required Provisions of Construction -state prevailing wages rates to be paid Contracts -sealed bids 1. 5%bid bond -addenda to bid documents(5 days prior to bid 2. 100%payment&performance bond opening&in writing) 3. 5%maximum retainage -bid modifications/withdrawal allowed up to bid 4. Enforcement of payment of general opening contractor to subcontractor(49-41b) -public opening of bids S. Sub securities for retainage(3-112a) -award to lowest,responsible,qualified bidder 6. Nondiscrimination clause(4-114a) Unallowable Project Costs 7. Executive Order 3 -any costs to acquire ROW 8. Prevailing State Wage Rates(31-53) -preparation of applications 9. Executive Order 17 -cost of pipes larger than 8"dia. 10. Contractor exempt purch cert.(Reg 18)- -fire hydrants 11. Time for project completion Plans 12. Liquidated damages cgver sheet with project area man 13. Change order profit amounts detailed map: 14. Insurances streetline,pavement,sidewalks,curbs, Worker's Comp driveways,houses w/house numbers,water -Contractor: main,service connections that consider entry Comp&General Liability($1M) point into house,wells,septic/sewer locations Property Damage($0.5M) on private property,utility poles,utilities within Comprehensive Auto Liability $1 p ty( M) street{storm,sewer,gas,exist.water},street Property Damage($0.5M) names,project limits,legend, schedule of homes -Owner: to be connected to water,water main design, Protective Liability($1M) note&detail-sheet: Property Damage($0.5M) typical plan/profile of connection,pavement, Type of Contract sidewalk,curb,minimum separation distance, Lump sum or fixed price or combination yard restoration,pipe trench&bedding,well Construction Contract Procurement Reqmts abandonment, Must provide maximum,open and free Specifications competition and avoid noncompetitive practices, bid schedule,protection of traffic,trench bid collusion,conflicts of interest,unnecessary excavation&restoration(soil&rock, lawn vs experience and bonding requirements,local roadway),pavement replacement,water service requirements that give certain bidders extension(curb valve&box,meter vault& preference meter,service pipe&fittings, inside plumbing, Advertising pressure reducing valve,service taps& If cost less than$25,000,need 3 prices, responsibility,warning tape),well otherwise must go to public bidding. abandonment,methods of measurement,pay Public notice limits,basis of payment, 10 days from last pubic notice to bid opening General Overview of Package Bid documents must contain the following: invitation to bid,bid schedule,bidder's -statement of work to be performed, qualification statement,non-collusion affidavit, plans/specs,schedule completion time bid bond,contractor's wage cent.form,state -terms&conditions of contract to be awarded wage rates,weekly payroll cent.form,contract -method of: bidding,bid evaluation,and award between town&contractor,plans,technical of bid specifications, -responsibility reqmnts for evaluating bidders `'- -Privity statement"" 080198 Page 1 of 4 DRAFT B.U. Customers Refunda a Advance Pa t Agreement /KGB 1.) Parties to the Agreement: The following are able and willing to agree: Company: The Connecticut Water Co., 93 West Main St., Clinton, CT 06413 Applicant: Town of South Windsor 2.) Life of the Agreement: This Agreement shall continue.in effect for the useful life of the utility plant installed hereunder, except that the provisions of Sections 8 and 9 will terminate 10 years from the date of execution hereof. 3.) Subject of Agreement: The Company shall acquire, install and provide with water the following described utility plant within a reasonable time after the execution of this Agreement: Place of installation: Town: South Windsor Street: Miller Rd., Barber Hill Rd. Description of plant to be installed: Mains: Diameter, type and length: 2450' of 8"DIP Water Main Service Connections: Diameter, type and number: 12-1" Other Plant: 4.) Consideration_for Agreement: The Applicant shall pay to the Company an advance equal to the actual cost (including but not limited to all special cost factors listed below) of acquiring and installing the required plant, in the following manner: (a) upon the execution of the Agreement payment in full of the then estimated cost (as determined by the Company) in the amount of $210 00 (b) upon completion of the installation and determination by the Company of the actual cost, payment of the total actual cost, less any prior payments, within 30 days after billing. Any amounts paid in excess of the actual cost will be refunded to the Applicant within 30 days after actual cost determination. Additional costs to be borne by the Applicant at no cost to the Company include all excavation and backfill required for service installations, and rock or unsuitable excavation costs. The Applicant shall provide an easement in accordance with the Company's standard format for all/any company owned facilities on private property. Costs shall be determined in accordance with the general accounting practices of the Company. 080198 Page 2 of 4 Meter horn costs included in this contract are as follows: Size Quanti Unit Cost Amount 5/8"x 3/" 12 $99.00 $1188.00 ' Special cost factors: 5.) Agreement as to Roadway: Applicant agrees to have all roadway graded to within 12 inches of finished grade and to have grade and line to street clearly marked prior to pipe installation. Roadways will be suitable for the passage of heavy vehicles and for stringing pipe where practicable. If at any time prior to acceptance by the Town of the street in which the pipe shall be laid, grades of the roadway are changed, the Applicant shall reimburse the Company the full cost of any adjustments in elevation of the pipe or other plant which may be necessary because of such changes. 6.) Limited Service: If any property to be supplied by a main extension to be installed pursuant to this Agreement is at such an elevation that, in the opinion of the Company, adequate pressure cannot be furnished at all times, the Applicant may be obligated to execute a Limited Service Agreement to be recorded in the Land Records of the municipality in which such property is situated. 7.) Conformance to Company Rules and Regulations: This Agreement shall conform to the Rules and Regulations (including main extension regulations) of the Company now in force and on file with the Department of Public Utility Control of the State of Connecticut, which are made a part hereof. In addition, curb boxes will be locked until a satisfactory inspection of the service line is completed from curb to home and a meter horn is located in the home. 8.) Company Agreement as to Refunds: A refund of $See ``A" will be made by the Company to the Applicant for each new metered service connected to the main extension installed pursuant to this Agreement within 10 years from the date of execution of this Agreement. The combined refunds will not exceed the amount of the total advance payments made by the Applicant. Refunds will be determined yearly on the anniversary date of this Agreement based on the formula approved by the DPUC. No refund shall be payable to the Applicant pursuant to this Section 8 for any new metered service connection for which a customer makes an equitable advance pursuant to the requirements of Section 9 hereof. i 0 080198 Page 3 of 4 9.) 8 rvice to Parties other than the Orisinal Applicant: For a period of 10 years from the date of execution of this Agreement, the Company will require any new customer seeking metered service through a service connection to the original main extension installed pursuant to this Agreement to advance his equitable share of the cost of such original main extension to the Company. That amount shall be reimbursed to the original Applicant who has advanced the cost of such original main extension. If there is more than one original applicant, said reimbursement shall be distributed equitably among said applicants. 10.) Ownership of Plant Installed: The main extension and related service connections and other plant installed pursuant to this Agreement, exclusive of the curb box, shall be the property of the Company. The curb box shall be the property of the Applicant and he shall be liable for its maintenance, its proper grade, and any legal or other actions stemming from or related to the curb box. 11.) ians of Parties: This Agreement shall bind and inure to the heirs, executors and administrators, successors and assigns of the parties hereto, but neither the sale nor transfer of his property by the Applicant, nor any other assignment hereunder shall relieve the Applicant of his obligation under this Agreement, unless the written consent of the Company is first obtained. The Applicant agrees to pay fire protection charges for company facilities on private property at public fire rates until such time as the Town and/or Association agrees to pay them. Any address or name changes made by the Applicant must be furnished to the Company _ in writing. The Company's inability to deliver refunds (per Paragraphs 8 and 9 of this Agreement) to the Applicant because of a changed address shall postpone all future refunds until an address change is received from the Applicant. Furthermore, no refunds will be issued or reissued after 10 years from the date of execution of this agreement. The Company will increase the size of they 12.) Special Conditions: The Apphcant agrees that pa v facilities installed at the direct incremental cost f materials and installation w e Com an deems necessary. The cost shall be determined in a cordance with the standard accounting practices and procedures as an roved b the D.P.U.C. Instant Refunds Due to the fact that the properties to be served are existing and seeking immediate water service the Co m an will allow "instant" refunds for all metered connections in 12lace b the end of the construction ro'ect. An adjustment will be made at the time of the final construction c st ad'ustment of the project to reflect these refunds. The refund am unt of wil a 1 to the connections m de nder this a reement. • 080198 Page 4 of 4 Executed and delivered at , Connecticut this day of , 2000. Witness: (two for each signature) THE CONNECTICUT WATER COMPANY By: Its: Manager of Region Operations Region: Northern Address: 25 North Rd., East Windsor, CT 06088 Applicant By: (Owner) DFL/vh 10/21/00 080198i .t.- Page 1 of 2 ®e THE TICUT WATER COMPANY MAIN EXTENSION REGULATIONS REFUNDABLE ADVANCE PAYMENT PLAN As approved by the Department of Public Utility Control, effective August 1, 1998. FOR INDIVIDUALS OR GROUPS OF CUSTOMERS, REAL ESTATE DEVELOPMENTS AND SUBDIVISIONS When the Company determines, in accordance with the guarantee rate on file with the Connecticut Department of Public Utility Control, that the estimated revenues from the requested main extension will be insufficient to cover all operating expenses and to support the investment by the Company, the Company will extend its mains under the following conditions: 1.) Applicants under this plan shall enter into a Customers Refundable Advance Payment Agreement with the Company, hereinafter called the Agreement, which shall require the Applicant to gay in advance to the Company an amount equal to the entire estimated cost, as determined by the Company, subject to the conditions in this plan. The estimated cost shall include the cost of service connections main to curb, excavation, pipe and fittings, road repaving, rock removal, replacement of unsuitable bedding and backfill material, inspection, and all other costs related to the job, including federal and state taxes, if any, payable by the Company with respect to the advance. Said estimated cost shall be adjusted to actual cost as soon as practicable after completion of the job, and the advance amount shall be adjusted accordingly. 2.) Diameters and types of pipe and fittings used in main extensions shall be determined and supplied by the Company. Pipe shall normally be no less than 8" in diameter. If it is necessary to install pipe larger than 8 in diameter to satisfy Applicant's requirements, the Applicant shall pay for the entire installation cost. If the Comoanv elects for other reasons to install nine which is greater than " in dinmPrPr, n 1 rnerc in excess of the cost to lav 8" main s all be borne Kv the Company, 3.) If a main extension requires additional facilities, such as standpipes and booster pumping stations, and such facilities are not then necessary to service the Company's existing system as a whole, the cost of such facilities will be included in the Agreement and paid by the Applicant. If such facilities are installed larger than required to serve the Applicant's requirements, the Company shall pay the cost of the excess capacity. 4.) Applicants must furnish the Company with two co ies of a town approved map drawn to scale showing layout of proposed roads andphouses, and must have filed a similar map with the Town Clerk. Before a main extension is undertaken, roads must have permanent grades established and must have been approved by the proper public authority. 5.) Applicants must provide when necessary, free of cost to the Company, a right of way or easement satisfactory to the Company, allowing it to install., maintain, extend, repair and replace mains and other necessary facilities and make connection thereto. 6.) All facilities shall be constructed in accordance with Company standard specifications and in accordance with special specifications and plans for the particular extension. All pipe shall have five feet of cover from top of ppipe to finished grade, proper bedding and suitable backfill. Construction prices shall be as quoted to the Company by its contractor or contractors. The Company shall inspect and supervise the work. 080198 Page 2 of 2 7.) The main extension and related service connections and other plant exclusive of the curb box shall be the property of the Company. The curb box shall be the property of the Applicant, and he shall be liable for its maintenance, its proper grade and any legal claims which may arise. 8.) If property to be supplied by a main extension is at such an elevation that, in the opinion of the Company, adequate pressure cannot be furnished at all times, the Applicant may be obligated to execute a limited service agreement, to be recorded in the Land Records of the municipality in which the property is situated. 9.) The Company will make a refund to the Applicant for each new metered service connected to a main extension installed pursuant to the Company's Refundable Advance Payment Agreement within a period of 10 years from date of advance payment, the combined refunds and payments made under Section 10 in no case to exceed the advance deposit. No refund will be made to the original Applicant for service connections for which a payment is required under Section 10. The refund will be at the Refund Rate on file with the Connecticut Department of Public Utility Control Refunds will be payable at the expiration of one year after the date of execution of the Agreement for each new metered service which qualifies as outlined herein. Refunds for subsequent qualifying new metered services will be paid thereafter on the anniversary date of the execution of the agreement, for a 10 year period, so long as the Agreement is in force and the other terms thereof are complied with. 10.) Any new Applicant seeking metered service through a service connection off a main installed pursuant to an existing Refundable Advance Payment Agreement, and within 10 years of the date such Agreement was executed, may be required to pay the Company an amount which, in the judgment of the Company, represents his equitable share of any original prepayment, less refunds. Such amount will be reimbursed to the original Applicant. If there is more than one applicant, said reimbursement shall be distributed equitably among the original applicants. 11.) The Agreement shall remain in effect during the useful life of the utility plant installed pursuant to the Agreement except that the requirements of Sections 9 and 10 above will terminate 10 years from the date of execution of the Agreement. 12.) Extensions designed to serve developments or areas which may be located considerable distances from the Company's existing mains will be considered separately on their own merits. The Company reserves the right to decline to undertake extensions which in its judgment would not be in the best interest of the Company or the community to be served. The Company also reserves the right to make modified proposals, subject to approval of the Connecticut Department of Public Utility Control, to suit other special circumstances. The Connecticut Water Company 25 North Road C000ieciticot�loiter P.O.Box 857 East Windsor, CT 06088-0857 Office:860.623.3355 Fax:860.654.1903 Customer Service:800.286.5700 October 6, 2000 Robert Deptula, Sanitarian Town of South Windsor 1540 Sullivan Avenue South Windsor, CT. 06074 Re-Water Main Extension - Barber Hill and Miller Roads, South Windsor Dear Mr. Deptula The water distribution system in South Windsor has been planned and constructed (to date) to provide adequate water quality, pressure and fire flows and is an integral part of the Company's Northern Western Distribution System that provides water service to eight towns in north central Connecticut. In order to provide uninterrupted service the system is highly dependant on;pipe:aoops for�r_edundancy. a;4'; The-existing 12-inch.water:mains:and the proposed;ex..tension on;Miller:Road:would create a;:critical loop by-paralleling approximately 1.5 miles of transmission main.on Rte 74 and, Sand Hill.Road,which is critical to the system operation._The parallel main will assist in the transfer of water across the system and provide both fire protection and domestic water service throughout. The system capabilities are supported by the Company's storage facility (Wapping Wood Tank) located just to the east of the project area. The proposed main is intended to serve an existing residential area that is fully developed. The Connecticut Water Company Main Extension Regulations (attached), as approved by the Department of Public Utility Control states "If the Company elects for other reasons to install pipe which is greater than 8" in diameter, all costs in excess of the cost to la 8" main shall be borne by the Company",..-The Company will install 12-inch water main on Miller Road and:wilhpay.for the difference:.irt_cost of 12"versus 8"Jt,is our opinion that D.E.P:'s formula.that would reduceahe grarrt.fund is not�applicable toahis;project or in conformance with the.. ompany'scRUles and Regulations.- Feel free to give me a call at (860) 669-8630 ext.3078 if I can be of further assistance on this matter or if any questions arise. Sinc ly, r C r aniel F. Lesnieski Jr. Manager of Region Operations Xc: Matthew B. Galligan, Town Manager—South Windsor William Warzecka, DEP Clifford McClellan, DPH TPO,JMcQ, MPW TEMPORARY CONSTRUCTION EASEMENT Know all men by these presents, that for Zero Dollar(s) and other valuable consideration received from the Town of South Windsor, Connecticut (hereinafter Grantee) each of the undersigned Grantors hereby grants to said Town, its agents and assigns, a Temporary Construction Easement upon the portion of the property in said Town as described on the map indicated below in which each of the undersigned Grantors has an interest as described in a deed recorded in Volume Page of the Land Records of said Town, to wit: Said Temporary Construction Easement is shown as`Temporary Construction Easement"on a map entitled "Temporary Easement to be acquired by Town of South Windsor, Connecticut, DESIGNED BY William R. Palmberg &Son LLC DATED 10-4-99" which map is to be filed in the South Windsor Town Clerk's Office. Said Temporary Construction Easement hereby being granted is for the purpose of the Grantee, its agents and assigns for the improvements within said easement. The Grantors grant to Grantee, its agents, and assigns, for the above-described purpose: 1. The right to enter upon the herein above described easement area and to drive vehicles and construction equipment on and across same; 2. The right to excavate in, or to disturb the surface of, said easement area; 3. The right to store and stockpile surplus or excavated material within said easement area during construction; 4. The right to survey said easement area and mark the location of the above described easement by suitable markers; 5. The right to do all other acts upon said easement area necessary for the efficient completion of the purposes stated herein. The Grantee, for itself, its successors and assigns, covenants and agrees with the Grantors, their heirs and assigns: 1. To indemnify and save Grantors, their heirs and assigns, harmless from any and all damage to property or person caused by the exercise of any of the rights granted hereunder, or by any negligent act or omission of it or any of its agents, servants and/or employees in the course of their employment; 2. To restore the land within said easement to as nearly its present condition as possible commensurate with the above provided uses; 3. All rights granted to Grantee hereunder shall be temporary and shall terminate one year after completion of construction. Signed and sealed at South Windsor, State of Connecticut, this day Of 11999. STATE OF CONNECTICUT ) ) ss. COUNTY OF HARTFORD ) Personally appeared who signed the foregoing instrument and acknowledged his/her signatures to be his/her free act and deed before me. Notary Public TOWN HALL USE ONLY Approved by Town Engineer Date \\TOW14_HALL\VOL2\ENGINEER\Projects-Constr ucdon\Hilton Drive\TEMPORARY CONSTRUCTION EASEMENT.doc R MEMORANDUM TO: JERRY IAZZETTA TOWN ENGINEER FROM: MELVIN C. STEAD,JR. ,� SUBJECT: MILLER ROAD WATER EXTENSION DATE: DECEMBER 8, 2000 Bob Deptula and I attended a meeting at the Connecticut Water Company to keep abreast of the proposal. A number of things were discussed, some concerning design and some concerning agreements that must be drafted and executed. First; the design/bid items: • CT Water requires all bidders to be pre-qualified and approved 15 days prior to bid opening. • CT Water has standard and typical specs and drawings to be incorporated in the bid and require North American made products. • CT Water will have an inspector on the job. • Separate bid items for hydrants. CT Water pays for them. • CT Water will do the taps and plumb to the curb stop. • Pressure reducing valves may be required on the service horns. • Service and meter to be to the front of the house. • Interior plumbing allowance fixed at$350.00. • At the twin 36 inch culvert (not the per foot main installation price) separate bid item. • Because of nearness to steel gas line cathodic protection is required. Other items: The question was raised about construction/contract management. Who is going to do it? The Town, its Engineer or the Water Company? Dan Lesnieski of CT Water indicated that they have worked any one of the three.ways mentioned. They also want to get an agreement signed that would indicate how that would be done. Dan was going to get some sample agreements to Bob. etc. The agreement would also indicate how the project would be paid. Up front, monthly, They also asked about whether the project would be extended out Barber Hill Road beyond the first 3 homes. Bob told them that would happen only if funding was approved and that was not final yet. I talked with Mike Anderson after the meeting about how the patch/overlay bid items would be set up. The overlay would be bid as an alternate. We talked about curb reveal and decided to also bid milling and curbing as an alternate. These items would not be funded through the grant but if we chose to go this route the pricing would be in place. The details of an agreement were not something Bob or I was in a position to talk about. The following were in attendance at the meeting. Michael Anderson Fuss & O'Neill Thomas DeSantos Fuss & O'Neill Mike Cunningham CT Water E. John King CT Water Valerie Hodden CT Water Daniel Lesnieski CT Water Bob Deptula South Windsor Mel Stead South Windsor CC: Bob Deptula '/ Mike Gantick NORTHERN REGION APPROVED WATER MAIN INSTALLATION CONTRACTORS—2000 1) B&J Construction Co.,Inc.646 South St.,New Britain,CT 06051 224-0306 2)++ Art Barber Excavating,Inc.PO Box 428,77 Meadowbrook Rd.,Ellington,CT 06029 875-3892 3)++ Bourgeois&Shaw,Inc.90 Wolcott Rd.,Simsbury,CT 06070 658-0448 4) Bradway Construction,Inc.396 West St.,Ludlow,MA 01055 413-583-6533 5) Coven Construction Co.,PO Box 427,Coventry,CT 06238 742-0796 6) D&M Construction Co.,PO Box 1405,Torrington,CT 06790 482-0260 7)++ Daddario Brothers,Inc.10 Southwood Rd.,Bloomfield,CT 06022 243-0339 8)++ Dufford Construction Co.,PO Box 109,240 Commerce St.,Glastonbury,CT 06033 633-0209 9)** Folsom Construction Co.,522 Burnham St.,South Windsor,CT 06074 528-8928 10) Gagliarducci Construction,PO Box 296,Springfield,MA 01151 413-543-6978 11) Gerber Construction Co.,616 Dart Hill Rd.,Vernon,CT 06066 875-6684 12) Guerrera Construction Co.,Inc.,154 Christian St.,Oxford,CT 06478 268-4159 13) Haluch Water,PO Box 510,399 Fuller Street,Ludlow,MA 01056 413-583-3196 14) Hinckley Construction Co.302 Washington Rd.,Enfield,CT 06082 745-1785 15) Johns Excavating,67 Ridge Rd.,South Windsor,CT 06074 644-5164 16)++ John Olender Corp.,23 Industrial Park Rd.East,Tolland,CT 06084 875-7903 17)++ Paganelh Construction Corp.PO Box 652,1064 East St.South,Suffield,CT 06078 623-0245 18) Phelps,Inc.PO Box 692,East Granby,CT 06026 627-8626 19) Sales Construction Co.,7 Woodland Hollow Rd.,W Locks,CT 06096 623-2925 20)++ Simscroft Echo Farms,Inc.PO Box 581,2 Farms Village Rd.,Simsbury,CT 06070 651-0231 21)++ J&H Slater Construction Co.,75 Commerce Way,South Windsor,CT 06074 528-5252 22)++ Spazzarinin Construction Co.,50 Post Office Rd.,Enfield,CT 06082 745-5683 23)++ R H White Construction Co.,Inc.PO Box 404,41 Central St.,Auburn,MA 01501 508-832-3295 24) Wilcox Construction Co.,Inc.,399 Broad St..,Windsor,CT 06095 688-9678 25) Wilcox Excavating Construction Co.,Inc.71 Willow St.,South Windsor,CT 06074 26) W H Williams&Sons,Inc.359 Moutain Rd.,Newington,CT 06111 666-4376 27)++ Wood Construction Co.,Inc.223 Wood Rd.,Somers,CT 06071 763-4185 28) Yancey Corp.,PO Box 413,27 Commerce St.,Glastonbury,CT 06033 633-0423 **Approved on trial basis ++DOT Quality Assurance Statement on File South Windsor Project Miller Road Residents 460 Michael Lanata 644-4372 filter 461 Wayne Martel 644-7230 filter 471 Paulette Farris 644-2226 filter 480 Raymond Shearer 644-4830 filter 488 Fred Schilke 644-9274 filter 496 Eward Rodonis 644-0761 filter 501 Richard Cyr 644-8102 filter 504 Jim Davis 289-5272 507 Breen 517 unknown Barber Hill Road Residents 10 Judy Kuehnal 644-1364 filter 20 Brad Case 648-9192 filter 34 Tom Dillon 644-0467 filter 42 Michael Pines 644-8861 filter 50 Joe Dzen 648-0554 76 Walter Twardowski 644-0453 204 Michael Dzen 644-1545 filter 244 Donald Dzen 648-9065 filter Foster Street Ext. Residents 969 Neil Coburn fJ,�,t AC et-ffr6t44-9765 977 Robert Yorgensen 644-2836 980 Dan Savino 644-0200 1009 Dick Kelbart 644-8200 1042 Brian Rivard 644-8378 filter 1043 Albert Ohlhof 644-0837 1051 Henry Sladyk 644-4259 1059 Paul Brown 644-7585 L SOUTH WINDSOR C hamber . Dhr . condnaed from Page B1 Continued from Page B1 1 Ask sure to TCE has been shown to dent of the Guymon Chamber of n. for Labor Day ttl>Ws R. cause liver tumors and kidney � �jufioklahoma,a 900 mem. ALL SAVINGS ARE OFF REGULAR PRICE problems in animals- of the From 19%to 1M he waseaecutive Soon after the discovery contamination,residents were giv- director of the Calvert County Cham- drink and water bar of Commerce in Prince Freder- f bottled were installed in other ick,Md.,which had about 5W MOM. AVON-353 W MAIN en bottled water to homes.With the filters,the water is bers• fine for drinking,bathing and MY Bisson began working with BRIS?OL-100 N MAIN 5 TE officials said. service organizations in L as a other use, representative for Optimists In Senyk,who has been leading the t e nano Louis and eventa. state investigation, said it was im ally ati a its director of growth in portant to put the residents' lives 1W.He later worked for the Nation- "back to normal"as quickly as poEt- Club in Toledo, Ohio, The sable and connect the homes to lines al Exchange serviced by the Connecticut Water andSerto whit rnati s peo Ransas seWith CO. He said he expects DEP Com- City,Mo., which help s eop ' / le r mi sioner Arthur J. Rocque Jr. to speech andhearingdisorders, sign an order for the plan and deliv Mitchell said the town chamber err er it to town officials next week. launched ��exe°enationwide d r "I'm very happy they're moving announced his re- with0 forward;' said Judy Kuehnel, the when Burnham ti Barber Hill Road resident found to be coffin- ti we ned tremendous response well was the first tamiiiated. and had some really qualified people . j . "If we can be assured to have we. step forward."he said. ter by spring,we can live with that Bissonwas the"consensus choice" ' —but not past that.The neighbors of the committee,which was made have all been very patient. But at UP offormer chamber presidentsand ` this point we.want to see some ac• other members, ssoT said, tion,"she said. Decker said Bison'sexperience hi Investigators are not certain working with volunteers and build ' what caused the contamination. hag membership in organizations ' Possible sources include farm activ. would be an important asset for the hies or an electric utility sub• chamber position:The chamber has station,he said. about500members. The town has been working with the state to find a permanent solu- tion since the problem was found. Town Manager Matthew B. GaM- gan said local officials are ready to mgve the$400,000 water-line exten- . sion project forward as soon as the �- Ask any of these Had DEP approval is received. A public hearing is tentatively FUCI1ItkC2 they'll tell you it's beG scheduled for Oct.2 in town hall. vision coffection done Save 10-500/0 LEGAL = _ ' — - Dr.Richard Ficb PUBLIC NOTICES who has done eaaNaN+a.aPiamMe and zamn.canNnK". _ The Fichman Eye Cent i 11011rNmleelsherobYalvertlhatMeEwlHart- laser with its radar- like C inpn�nest+nawwaanetdonsamembe► , 7 farsig p,M.imthe Town CaC c1u�c lfieuttliaiWlov+Ma _ Street.East Hartford. ' on Item: • Includes all dining,seating, 1 giH.ATIMERSTREETSUBDIVI510NPRE• umbrellas,accessories. �iwo ion"fon AND M Oft o tamed at VA : The Fichman E street. _. . . Rvr•P11Attt selection but etatt