December 3, 2009
Frank & Karen Demonte
190 Lawrence Road
South Windsor, CT 06074
Re: Information Request for Sewer Connection
Dear Mr. & Mrs. Demonte,
The Water Pollution Control Authority has informed me that you are concerned that
the existing sewer lateral pipe to your 190 Lawrence Road property is not located
conveniently to serve the house and that the WPCA has agreed to your request to
install a new sewer lateral. Attached is a plan of your property showing the existing
sewer lateral in the road to your property. Please check this information and mark
the plan to show where you would like a new sewer lateral to be located.
We have also shown an approximate location of the well and a circle around the well
with a 25' radius. Please check and confirm this location and indicate the actual well
location (if known) if different than that shown. This information is required in order
to meet the State Health Department requirement of a 25 foot separation distance
between the well and the building sewer.
Please return the enclosed plan with the information for your property to me at the
address above within the next two weeks. The installation of the lateral will probably
occur next spring.
Thank you for your assistance in this project. If you have any questions please call
me at 644-2511 ext 245 or Bobb Grillo of 644-2511 ext. 257.
Sincerely,
?ffre��!Iittle,
P.E.
Town Engineer
cc: Michael J. Gantick, P.E., Director of Public Works
C. Fred Shaw, Superintendent of Pollution Control -
w
v.N=334.9 Approx. -
v.S=333.c5' Top of Foundation
V.W=333.9 BM E Elev.=3474 #'99
v. I
mwrcrtvr am warm
NW=334.1 Z Mog Noil Set 1' Up Door Sitl �,.
Door Sill SNE7"#2095 w/Riser Elev.=34
Elev.=345.0.9 ELEV. = 341.98
345.4 Wooded
344.30 Catch Basin 34t.X l49,�..� 145SNET
34333
Grate=337 20
In v.=333.3 5255
340.3 Q
Catch Basin 4,.. `P�a�;_� ;..4'iGtulti 4 7 5,,
Grate=337.04 �..,., S ° �t'� 4" . _ t 26+00
Inv.SE=332.9 �. °<`
x Inv.5=333.0 G W� SOR,35 ®�i,
338.3 In v.W=3,33.2 _ Pin S 300' 8 3
lnu.NW=333.1 Y� r ;S" Fo d
v� N 6" �� >4 ' 34t.43 6 p0 t7- 73 6" SEAR
8" Man 343
-NS" (. EXSM 34 Foun _ /f o
r .. ..r4. x
Wo
33923 Mon. Post��`�:,•.., ) '
g PVC SE�M1'ER MAIN 0.30 fU
NV on. `,.. Well 2.7
2 c G% Found i Stoke
18 RCP ?? . ' .? a Sprin er
33 39 t- �-) 4 \ 4 Multi
crs 15" ca x
12 Twin 78a 20"f� ci ` 518" Elea=345.4
j15" ;J 12�'.. Vf ?g•R ° 3 Metal 339.3 208
339
Post
339.3 � X See 167
Wetf 338. ` 338 S For Meo:
.�12" 1 tump; i v' "Stoke To Foun,
71
.7 "a+
Conc. Elea=341.31
Stake q Catch Basin
'A0jU Approx. Grate=340.32
335,5 Top of Foundation In v.S=336.5
Approx, Catch Basin Elev.=340.9 Inv.NW=336.5
of Foundotio Grate=337.76 see 1679148
:lev.=338.5 in v N=334.6 Septic For Measure Down
x Conc. v.In S=334.5 In Reor To Foundation
Eleu=338,71 190 LAWRENCE ROAD
#140 SEWER LATERAL LOCATION
See 1679149 1" = 40' DEC. 2009
For Measure flown
To Foundation
LAWRENCE ROAD SEWER EXTENSION ESTIMATES 8/29/2007
UNIT ESTIMATED ESTIMATED
ITEM UNIT COST COST
/UNIT QUANTITY
NORTH EXTENSION
300' north of Vincent to just north of Cliffwood 1100 ft
Survey/As-Built L.S. 15,000.00 1 15,000.00
Soil Borings L.S. 2,000.00 1 2,000.00
Erosion&Sediment Control L.S. 5,000.00 1 5,000.00
Dewaterin L.S. 5,000.00 1 5,000.00
8"Sewer Main L.F. 82.00 1,070 87,740.00
6"Lateral L.F. 44.00 420 18,480.00
Sanitary Manhole EA. 3,850.00 4 15,400.00
Gravel for Unsuitable Backfill C.Y. 22.00 800 17,600.00
Sub rade S.Y. 2.00 1,678 3,356.00
Subbase C.Y. 25.00 280 7,000.00
Processed Aggregate Base TON 27.00 604 16,308.00
Bituminous Concrete Class 1 TON 78.00 193 15,054.00
Loam &Seed S.Y. 7.00 80 560.00
Maintenance&Protection of Traffic L.S. 5,000.00 1 5,000.00
Subtotal 213,498.00
20% Misc. &Contingency 42,699.60
Total 256,197.60
SOUTH EXTENSION
Spinners Run to 580'south
Survey/As-Built L.S. 10,000.00 1 10,000.00
Soil Borings L.S. 1,000.00 1 1,000.00
Erosion &Sediment Control L.S. 3,000.00 1 3,000.00
Dewaterin L.S. 3,000.00 1 3,000.00
8"Sewer Main L.F. 82.00 580 47,560.00
6" Lateral L.F. 44.00 120 5,280.00
Sanitary Manhole EA. 3,850.00 2 7,700.00
Gravel for Unsuitable Backfill C.Y. 22.00 300 6,600.00
Sub grade S.Y. 2.00 800 1,600.00
Subbase C.Y. 25.00 133 3,325.00
Processed Aggregate Base TON 27.00 288 7,776.00
Bituminous Concrete Class 1 TON 78.00 92 7,176.00
Loam &Seed S.Y. 7.00 22 154.00
Maintenance&Protection of Traffic L.S. 3,000.00 t 1 3,000.00
Subtotal 107,171.00
20% Misc. &Contingency 21,434.20
Total 128,605.20
TOTAL BOTH EXTENSIONS 384,802.80
TOWN c LERK OCT 2 9 2007
Proposed Lawrence Road Project-Public Information Meeting
AGENDA
TOWN OF SOUTH WINDSOR 7:00 P.M.
TOWN COUNCIL CHAMBERS OCTOBER 29, 2007
1. Introductions
2. Background
♦ Septic Systems
♦ Soil Conditions
♦ Street Conditions
3. Project Description
♦ Sewer System
- Lateral Locations
- Sewer Assessments
♦ Street/Road Improvements
4. Time Frame/Schedule for Implementation
S. Questions
i
f
1 �
M
Jr`
I _ a
Lawrence Road sewer Assessments
Aug-07
Residence
#64 Front Line 225 Lateral Base Cho. Frontane Total Annual Payment(15 yrs.Ca)-6%)
Rear Line 230
Frontage 227 227 $997 $1,993 7491 $10,481 $1,018
#74 Front Line 111.25
Rear Line 90
Frontage 102.75 102 $997 $1,993 3366 $6,356 $617
#96 Front Line 150
Rear Line 150
Frontage 150 150 $997 $1,993 4950 $7,940 $771
#152 Front Line 187.19
Rear Line 190.08
Frontage 188.346 188 $997 $1,993 6204 $9,194 $893
#140 Front Line 186.13
Rear Line 184.2
Frontage 185.358 185 $997 $1,993 6105 $9,095 $883
#190 Front Line 134.47
Rear Line 216.17
Frontage 167.15 167 $997 $1,993 5511- $8,501 $826
#208 Front Line 135.51
Rear Line 124.63
Frontage 131.158 131 $997 $1,993 4323 $7,313 $710
#220 Front Line 150
Rear Line 119.01
Frontage 137.604 137 $997 $1,993 4521 $7,511 $730
#232 Front Line 150
Rear Line 134.18
Frontage 143.672 143 $997 $1,993 4719 $7,709 $749
#278 Front Line 221.42
Rear Line 182.94
Frontage 206.028 206 $997 $1,993 6798 $9,788 $951
#244 Front Line 150
Rear Line 150.59
Frontage 150.236 150 $997 $1,993 4950 $7,940 $771
#256 Front Line 150
Rear Line 150 $771
Frontage 150 150 $997 $1,993 4950 $7,940
#268 Front Line 161.42
Rear Line 150 $795
Frontage 156.852 156 $997 $1,993 5148 $8,138
#279 Front Line 137.12
Rear Line 110 $694
Frontage 126.272 126 $997 $1,993 4158 $7,148
#269 Front Line 136.6
Rear Line 136.6 $726
Frontage 136.6 136 $997 $1,993 4488 $7,478
#259 Front Line 136.6
Rear Line 140 $730
Frontage 137.96 137 $997 $1,993 4521 $7,511
#249 Front Line 136.6
Rear Line 130 $717
Frontage 133.96 133 $997 $1,993 4389 $7,379
#239 Front Line 150
Rear Line 150.29 $771
Frontage 150.116 150 $997 $1,993 4950 $7,940
#225 Front Line 200
Rear Line 195 $925
Frontage 198 198 $997 $1,993 6534 $9,524
#215 Front Line 155.44
Rear Line 150.59 $781
Frontage 153.5 153 $997 $1,993 5049 $8,039
Assessment Totals $162,925
Estimate Construction Cost $384,803
Sewer Fund Capital Reserve Expenditure $221,878