HomeMy WebLinkAbout124 Commerce Way (5) DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
KAHN & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
I li ndsor Steel
South Windsor, CT
Special Inspection #1
Plovv,niber 21, 2000
Visited site to view footing excavation. Generally very sandy, loose
Foot nos formed +or azure per i meter walls. Pour to occur
latter that day.
William. Bayer
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
KAHN & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
Windsor Steel
South Windsory CT
Special inspection ##2
November 22, 2000
Visited site to view foundation progress. Office perimeter footings
stripped. Forming Warehouse East wall footings. Blankets on site to
cover after pouring. Footing reinforcing on chairs.
William Bayer
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
KAHN & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
Windsor Steel
South Windsor, CT
Special Inspection $#y
November 29 a 2000
n`►far�::rac�a_rse perimeter f t�oti gs pour ed, except at dock area. P'Ir�t of
Office wall poured. some column anchor bolts omitted. Told Mountf ord
they must gpt detail from steel erector for corrective action. The type
of expansion boltz, embedment etc. must be all included.
William Buyer
DAVID KAHN,P E. WILLIAM A.BAYER,P.E.
KAHN & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-6464440
FAX 860-646-9518
Windsor Steel
Sut.ith Windsor,, CT
Special Inspection #4
Dec. 10 2000
Stripping forms at Office foundation walls, front and left sides, Rear
Warehouse footings not poured yet. Dock footing at Southwest corner
complete. Had discussed with GC the placing of stone under footing due
to groundwater at this elevation. This stone was placed.
Forming Office foundation walls at right side. Noted loose material in
Warehouse area. All must be compacted and tested prior to any slab
pouring.
William @a
• ,. ..... . „r„ .. ,. r,. .. .. r..t..i,. ,..r,..l.'aL,u�I.N..r•.a.n•..•.,..,r4.rl..•6r.rW.aYlrswr,........ ..,......«...».
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
KA H N & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
Windsor Steel
S,,uth Windsor, CT
Special I nspect i Dn #5
Dec, 11, 2000
Visited site to view wall pour. Wall being readied for pour was at West
side of Warehouse. Reinforcing steel was in place. Anchor bolts were
being set; at about Noon. Pour was schpdul ed for 2:04 P.M.
William Bayer
r
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
-- KA H N & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-64&9518
Windsor Steel
South Windsor, CT
Special Inspection #6
January 15, 2001
Major wall pour scheduled. Balance of Warehouse foundation walls.
Reinforcing was in place with ties at column piers. Anchor bolts Were
partially installed, with balance being set as l watched.
William Layer
DAVID MHN,P.E. WILLIAM A.BAYER,P.E.
KA H N & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
Windsor Steel
South Windsor} CT
Special Inspection #7
February 2, 2001
Office wood trusses being erected. Plywood sheathing at Office being
placed right behind truss installation. Office Walls being sheathed.
Front canopy at Office being framed.
Balance waiting for prefab steel .
William Ba r
1
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
-- KAHN & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9516
Windsor Steel
South Windsor, CT
Special Inspection #S
Feb. 10, 2001
Front office canopy framed and sheathed. Front office roof completely
sheathed and closed.
Demising wall between Warehouse and Office complete. Wall ties from
block to columns in office visible and correct.
William' Bayer
G ;
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
KAHN & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
Windsor Steel
South Windsor, CT
Special Inspection #9
Feb. 18, 2001
Steel frame erection in Warehouse begun. First bay at North end in
place With, frames and one bay of purl i ns erected.
William E+ er
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
-- KA H N & BAYER CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-646-9518
Windsor Steel
South Windsor, CT
Special Inspection #10
Feb. 225 2001
Warehouse prefab steel progressing. All frames in place. Approximately
90 of purl i ns in place. Approximately 75% of warehouse wall gi Ets
installed. Frames being plumbed with cables and guys.
William Bayer
DAVID KAHN,P.E. WILLIAM A.BAYER,P.E.
KA H N & BAY E R CONSULTING STRUCTURAL ENGINEERS
48 PURNELL PLACE
MANCHESTER,CONNECTICUT 06040
TEL.860-646-4440
FAX 860-64fr9518
Windsor Steel
South Windsor, CT
Special Inspection J�11
March 269 2001
Entire steel frame in warehouse has been erected. Frames are being
braced temporarily with guy wires, All wall gi its are up and all "all
siding has been erected. All roof purl i ns are in place, with
approximately 50% of the roof panels in place. The steel framing for
the mezzanine has been completed.
It appears that bad weather is only reason that roof is not complete.
'The crane runways are all on site, but not erected yet.
_ There appears to be little or no frost inside warehouse, so that once
enclosed, slab should be able to proceed. This should be verified when
slab grading takes place.
William Bayer, P.