January 20, 2016
Mayor Tom Delnicki
Town of South Windsor
1540 Sullivan Avenue
South Windsor CT 06074
Dear Mayor Delnicki:
RE: CGS 8-24 Referral for the Acquisition of Street and outdoor Lighting Equipment from
Eversource Energy and Retrofitting with LED Technology
I am pleased to advise you that the South Windsor Planning and Zoning Commission, at its
Regular Meeting of May 12,2015, by a vote of 4—2 with Commissioners King, Kuehnel,
Marrero, and Pacekonis voting for; Commissioners Dexter and Carroll voting against; and
Commissioner Bonzani abstaining, forwarded a favorable review of the above mentioned
project.
For your reference,minutes regarding this referral from the May 12,2015 meeting are enclosed.
Sincerely,
Bart Pacekonis, Chairman
PLANNING&ZONING COMMISSION
BP/llz
Enclosure
cc: Town Manager
Director of Public Works
Town Attorney
Clerk of the Council
TOWN OF SOUTH WINDSOR
PLANNING &ZONING COMMISSION
MINUTES -2- MAY 12 2015
5. The fire marshal has reviewed this request. He is ok with the storage on the side; however he has asked
Lowe's to keep the fire lane around the building clear and has required them to relocated pallets from that
area.
6. The wording of the T& C permit regulation is that, "Temporary and conditional permits may be granted by
the Commission for a use which is not specified elsewhere in these regulations for a period not to exceed
two years. Such approval may be given after a Public Hearing if, in the judgment of the Commission,the
public convenience and welfare will be substantially served, and the appropriate use of neighboring property
will not be substantially or permanently injured,and traffic and other hazards will not result from such use."
If this application is approved,the planning department has no modifications to request.
No one from the public spoke for or against the application.
Commissioner Dexter asked about the seasonal use and when the area would revert back to the smaller size. Mr.
Owens replied after July the smaller configuration will be used with no use in winter months. Commissioner
Marrero asked about the outdoor display at the front of the store. Ms. Lipe stated it was included in the original
2011 approval.
The Chairman closed the public hearing at 7:38 p.m.
REGULAR MEETING/MADDEN ROOM
CALL TO ORDER: Chairman Pacekonis opened the Regular Meeting at 7:3 8 p.m.
PUBLIC PARTICIPATION:
NEW BUSINESS: Discussion/Decision/Action regarding the following:
1. Town Council CGS 8-24 Referral for the Acquisition of Street and Outdoor Lighting Equipment from
Eversource Energy and Retrofitting with LED Technology
Town Councilor Steve Wagner described a program to purchase street and outdoor lighting equipment from
Eversource which would then be retrofitting with LED technology resulting in cost savings to the town. .
Councilor Wagner stated the Energy Committee has been working since last fall developing a plan to convert
town street lights from high pressure sodium lights to LED technology which uses considerably less energy. A
handout was distributed to the Commissioners. The program would require the town to buy the street lights
from Eversource,which presently charges the town$460,000 annually, and then to convert the lights to LED
technology. This would result in energy cost savings to the Town after conversion of about$300,000 a year
however maintenance and insurance costs would be added. The dark sky compliant LED technology is more
efficient and requires fewer fixtures to create current levels of illumination. Bulb life is proposed to be
significantly longer(20 years compared to the present 5 to 6 year life time)which makes accepting maintenance
costs easier. East Hartford has replaced most all their street lights to LEDs which can be observed there.
The Chairman asked about lighting for condominium developments in town. Mr. Wagner stated this project
relates to town owned lights and if condo associations want to participate they could purchase their own lights
at similar pricing negotiated for the town.
Commissioner King asked whether the cost of retrofitting was justified when all street lights produced will soon
be required to have LED technology. The Chairman asked if Eversource will be independently retrofitting the
street lights within the next 5 years. The Councilor stated studies show costs of LED lights going down 12%
TOWN OF SOUTH WINDSOR
PLANNING &ZONING COMMISSION
MINUTES -3- MAY 12 2015
each year where as labor costs rise at least 2%each year. Delaying the project could cost the town"a couple
$100,000".
Commissioner Marrero stated the utilities gave towns funding when the traffic signals were converted to LED
and asked if the utility company had been contacted for this project. Mr. Wagner noted an estimated incentive
of'$271, 698 provided by the State.government and perhaps the utility. Eversource will be responsible for all
conduits going to the poles but the Town would be responsible for the poles and fixtures. The maintenance of
the poles would then be contracted out. East Hartford and three other towns in Connecticut have made the
change over.
A contractor will do an investment grade audit of all street lights in town which will provide the basis for
negotiations with Eversource. Chairman Pacekonis noted flood lights on utility poles which shine on
commercial properties. Mr. Wagner stated it will be addressed in the audit. Once the lower rate from Eversource
is established bills will be audited to assure the Town is not being overcharged. The full audit is estimated to be
complete in October and then a contract can be negotiated. Commissioner Carroll asked about upfront costs for
the audit. Mr. Wager answered$70,000 or$80,000.
Commissioner Bonzani arrived.
Commissioner Kuehnel made a motion to make a referral with favorable report.
Commissioner Marrero seconded the motion.
Chairman Pacekonis re-appointed Alternate Commissioner King to be seated for Commissioner Foley.
The motion passed 4 -2 with Commissioners King,Kuehnel,Marrero, and Pacekonis voting for,
Commissioners Dexter and Carroll voting against, and Commissioner Bonzani abstaining.
2. Appl. 15-14P,Ticket Network Site Plan-review of required landscape buffer on property located at 83
Gerber Road,I zone
Ticket Network facilities manager, Mr. Seth Resnickoff,requested by email to reschedule the landscape buffer
plan review.
3. Preliminary discussion with Ticket Network regarding expansion of farming activities on property
located at 83 Gerber Road, I zone
Commissioner King abstained from participating in the discussion and recused herself as an employee of Ticket
Network.
Mr. Darnell Goldson,public relation director for Ticket Network, discussed the potential of adding a herd of
goats,which Ticket Network would like to house temporarily in order to save them from euthanasia,to their
farming activities permitted by a temporary and conditional permit which expires in June. The herd of 100
neglected goats has recently been taken in by the State which has received `about a dozen' offers to take them.
The State will be releasing a plan for the herd in the coming weeks.
Director of Planning Lipe stated a temporary and conditional permit through the public hearing process would
be the way to address concerns about best animal practices and the potential of odor and noise. A management
plan and manure plan would be reviewed by the Health Department.