May 15 , 1993
Mr . Bruce Kelley
RSK-KELLCO, Inc.
1744 Ellington Road
South Windsor, CT 06074
RE : Fitch Meadow Development
John Fitch Boulevard, South Windsor
Dear Mr . Kelley:
The South Windsor Water Pollution Control Authority, at its regular
meeting of March 16 , 1993, approved the Fitch Meadow Development as
detailed on plans entitled "Fitch Meadow, 62 John Fitch Boulevard,
prepared by Torres Engineering, Dated 6/21/91 , Last Revision
1/23/92" , subject to the following conditions :
1 . .Town Engineering technical approval obtained ;
2 . Developer shall either install manhole 145 feet north of
existing manhole identified on plans for Sanitary Sewer
Construction, Sewer Contract A Asbuilt Drawings , dated
10/3/72 , Drawing #3-A, Station 13+32 . 5, perpendicularly
crossing Route 5 to connect to existing sewer line; or if
possible, the contractor has the option of connecting
directly into said manhole at Station 13+32 . 5 , running
perpendicularly across Route 5 and ending at the existing
manhole 118 feet east of proposed John Fitch Meadow Lane; -
3. A 20 foot permanent easement for sewer maintenance is
required across all private property within cluster develop-
ment if the final plan approved establishes Fitch Meadow
Lane as a public road. Said permanent easement shall be
documented in the property records of properties involved .
4. All manholes will be placed in the middle of the blacktopped
roadway and manhole covers shall be no deeper than or. raised
by any more than one-quarter inch .
5 . Final Authority approval and acceptance of the sanitary
sewerage system will be given once sewer has been
installed and inspected by the Town staff , and based
upon the written verification of the Town staff that
said sanitary sewer was installed by the developer in
r Mr. Bruce Kelley
May 15, 1993
Page 2
substantial conformance with the design plans previously
approved by the Authority, and meeting all Town regulations
and appropriate technical specifications relating to
sanitary sewer construction ; and
6 . This approval letter must be superimposed into the final
approval plans .
Very truly yours ,
.... ....
................ ........-..............1fLf `_a.........
..._._.........._.............................
..
J sep� Ca ino, Chairman
Water Pollution Control Authority
Town of South Windsor
cc: Jean E . Zurbrigen , Town Manager
Michael J. Gantick , Director of Public Works
Jerry lazetta, Town Engineer
Marcia Banach , Director of Planning
John Collins, Chief Building Inspector
John McCahill , Zoning Enforcement Officer