July 18, 1997
Mr. John F. Reichle
246 Graham Road
South Windsor, CT 06074
RE: Reichle 2-lot subdivision
Foster Street
SOUTH WINDSOR, CT
Dear Mr.Reichle:
The South Windsor Water Pollution Control Authority, at its regular meeting of July
15, 1997, gave approval for the connection to the Town's sewerage system of a 2-lot
residential subdivision at the westerly side of Foster Street, as more specifically
shown on Topographic Plan entitled "Resurvey Prepared For John F. and Mary M.
Reichle - Foster Street - South Windsor, Connecticut" by Design Professionals, Inc.,
South Windsor, Connecticut, Project No. 97-983, Drawing No. 4/4 dated April 4, 1997,
no revisions, and subject to the following conditions:
1. Technical approval of the Town Engineering Department.
2. Final Authority approval and acceptance of the sanitary sewerage connection
will be given once the sewer lines have been installed and inspected by the
Town staff, and based upon the written verification of the Town staff that said
sanitary sewer lines were installed in substantial conformance with the design
plans previously approved by the Authority, and meeting all Town regulations
and appropriate technical specifications relating to sanitary sewer construction.
3. Applicant must submit final plan incorporating the hand-drawn information
on Mr. Perna's exhibit map. Mr. Perna's exhibit map will be retained by the
Engineering Department pending receipt of final plan.
4. Both sewer lines must be serviced by pumps.
5. An emergency holding tank of at least 250-gallon capacity must be provided to
ensure emergency 24-hour holding capability.
6. Provision must be made so that electrical service can be plugged into auxiliary
emergency power when necessary.
Mr. John Reichle
July 18, 1997 Page 2
7. All necessary fire safety provisions must be met.
8. Payment of sewer benefit assessment.
9. Existing sewer easement must allow connection of Lot#l.
10. This approval letter must be superimposed on the final approval plans.
Very truly yours,
Joseph J. Carino, Chairman
Water Pollution Control Authority
JJC:rt
cc: Matthew Galligan, Town Manager
Michael J. Gantick, Director of Public Works
Jerry Iazzetta, Town Engineer