August 5, 1998
Mr. Steven Richards
United States Post Office
6 Griffin Road
Windsor, CT 06006
RE: United States Post Office
Clark Street
SOUTH WINDSOR, CT
Dear Mr. Richards:
The South Windsor Water Pollution Control Authority, at its regular meeting of July 14, 1998,
gave approval for the connection to the Town's sewerage system of a commercial building at
Clark Street, as more specifically shown on plans entitled "United States Post Office - South
Windsor MSBD - South Windsor, Connecticut 06074-9998" prepared by AN Consulting
Engineers, Newington, CT; The Mead Group PC, West Hartford, CT; and Ferrero Hixon
Associates LLC, Simsbury, CT; USPS File No. B32300; Drawings C4.01- Site Drainage and
Utilities, C7.01 - Off-Site Water and Sewer Utilities, and C8.01 - Off-Site Water and Sewer
Details, all dated January 26, 1998, no revisions; and subject to the following conditions:
1. Technical approval of the Town Engineering Department.
2. Final Authority approval and acceptance of the sanitary sewerage connection will be
given once the sewer line has been installed and inspected by the Town staff, and based
upon the written verification of the Town staff that said sanitary sewer line was installed
in substantial conformance with the design plans previously approved by the Authority,
and meeting all Town regulations and appropriate technical specifications relating to
sanitary sewer construction.
3. Connection shall be made at a manhole located at the northern terminus of the sewer line
in Clark Street.
4. As-built drawings, properly defining the location of the sewer line from the existing
manhole to the Post Office property, shall be provided to the Town.
5. An easement, in a form acceptable to the Town Attorney, shall be provided across
private property at the southerly side of the Post Office property.
Mr. Steven Richards - 2 - August 5, 1998
6. This approval letter must be superimposed on the final approval plans.
Very t y yours,
Thoma i dson, Chairman
Water pollution Control Authority
TH:rt
cc: Matthew Galligan, Town Manager
Michael J. Gantick, Director of Public Works
Jerry Iazzetta, Town Engineer
Marcia Banach, Director of Planning
John Collins, Chief Building Inspector
TOWN OF SOUTH WINDSOR
WATER POLLL"TION CONTROL AUTHORITY .
APPLICATION FORM
Application No.
Date Received
Date Scheduled For
Applicant U.S. Post Office
Address 6 Griffin Road, Windsor CT 06006 Telephone No. 60 285-7139
Owner of Record on Land Records . U.S. Post Office
Owners Address 6 Griffin- Road, Windsor, CT 06006
Property Description:
Assessor's Map # Parcel # 1 Vol. 981 Page 209
Project Title: New Main Office, South Windsor CT
Inquiries to be Directedto: (name, address, to ephone no.) Steve Ric aids
U.S. Post Office, 6 Griffin Road, Windsor, CT 06006
I Approvals Previously Received (Check) IWA X P & Z ZBA
Purpose of Application: (Check all that apply)
1. Sewer Extension/Connection Residential Use
a. Subdivision
b. Single Unit
c. Other - 7xpTain-
d. Type o Approval: Concept Final
Sewer Extension/Connection -- Industrial/Commercial User
a. New Connection X
b. Request to Increase ooww ate
c: Change in Nature of Waste Discharge
d. Other Explain
e. Type o Approval: Concept Final
3. Appeal of Sewer User Charge
a. Residential
b. Industrial/Com
4. Sewer Assessment
a. Establish Sewer Assessment
b. Appeal of Sewer Assessment
c. Change in Use of Property
5. Regulatory Appeal ; Explain
6. Other Explain
pplicant igna a to
Xwner's4Silarm re ate
(See Reverse Side for Application Submittal Procedures)
Imssol"CAlapplicanon
11126M