HomeMy WebLinkAboutSite Plan - Conservation (376) TOWN OF SOUTH WINDSO CT 4 1984 .
INLAND WETLANDS AND.WATER
APPLICATION
THIS APPLICATION SHALL BE RECEIVIB BY THE
INLAND WETLANDS AGENCY ACTION INLAND WETLANDS AGENCY AT THE REGULAR-
APPLICATION NO. �wC LY SCHEDULED MEETING ON THE SECOND MON-
DAY OF THE MONTH AT THE TOWN HALL.
RECEIVED DATE THIS APPLICATION MUST BE FILED IN TRIPLICATE
PUBLIC HEARING DATE AT THE OFFICE OF THE TOWN CLERK TOWN OF
(if necessary) SOUTH WINDSOR, AT LEAST TEN DAYS PRIOR TO
COMPLETED APPLICATION THE REGULAR MEETING DATE.
PERMIT GRANTED DATE A SET OF PLANS MUST BE SUBMITTED TO THE
TOWN ENGINEER AT LEAST TEN DAYS PRIOR TO
PERMIT DENIED DATE THE REGULAR MEETING DATE.
PLEASE PRINT.
1. - uADAPPLICANT I
TEL. NO. i -ZSLri
ADDRESS1 Ir`x7'fl,� rI,Ll4j,1� 5T- CITY & STATE Iu1 11GE-( �/L� C6 fo8�
2. OWNER 0) r( Q/1 D O TEL. NO.
ADDRESS CITY & STATE _U1, MF/ Lb
3. LOCATION OF PROPERTY_-
a NAMES OF ADJACENT PROPERTY OWNERS_- tlI ).
STATE CLEARLY AND BRIEFLY
5. PURPOSES AND DESCRIPTION OF THE PROPOSED ACTIVITY AND THE .TIME ELEMENT INVOLVED.
�r�PULS+VT / tT �SDS TD v`A�ITyILy SELUs:1Z tw0�'� (.U61rtb2(t3�RSE
AS ! la &j oA j PLANS, Aa'r l�iEO
ATTENTION: THE APPLICANT UNDERSTANDS THAT THIS APPLICATION IS TO BE CONSIDERED
COMPLETE ONLY WHEN ALL INFORMATION & DOCUMENTS REQUIRED BY THE
I AGENCY HAVE BEEN SUBMITTED.
APPROVAL MAY ALSO BE NECESSARY FROM THE PLANNING AND ZONING COM-
MISSION.
U TMt -,46rEPiG1�,4�a-Tfl {.,gf3ttd{} -
AN APPLICATION FEE IS REQUIRED, CO ULT THE REGULATIONS.
A SIGN IS REQUIRED. CON T HE AT NS.
SIGNED: ��-
(Applicant) AST FQ-- J. 2.
SIR ..
(Owner)
Revised 9/20/82 ��
MEEHAN ASSOCIATES Consulting Engineers—Surveyors, P.C.
Sediment and Erosion Control Procedures
To be used during construction of a sanitary sewer from Clark Street
to Smith Street, South Windsor
JMJ Construction Company is proposing to install a 10" diameter sanitary sewer
from an existing manhole on Clark Street through land presently owned by
Hartman Tobacco to a point on Smith Street which will serve Pleasant Hills
Condominium. This sewer will also serve a development that J & R Realty is
proposing on the Hartman land. In general, all construction is to comply with
the requirements of the Hartford County Soil & Water Conservation District and
the South Windsor Inland-Wetlands Commission. Portions of the sewer installation
are under existing street pavement and normal prudent construction procedures
will be followed in these areas. Other portions, however, involve working along
the edge of wetlands, crossing a brook, and trenching overland through erodable
soil. Appropriate procedures will be followed for each of these areas. The
specific locations and procedures are outlined below.
Tk 1 (Sta 0 + 00 to Sta 4 + 00)
Install sanitary sewer between edge of Clark Street and adjacent
wetlands.
Objective: Protect stream and wetlands from siltation caused by construction.
Procedure: Install silt fence of staked haybales along all downslope perimeter
as close as practical to the trenching. Maintain fence until
veget&.tion is re-established. Do not disturb land in area between
fence and wetlands.
Task 2 (Sta 4 + 00 to Sta 4 + 50)
Install sewer under brook in concrete brook-crossing structure as
detailed on construction plans.
Objective: Minimize downstream siltation due to construction in brook channel.
Procedure: Reroute brook temporarily by installing two 20' lengths of 30"
corrugated aluminum pipe 25 feet east of and parallel to the
brook. After pipe and outlet channel are in place, cut through
brook bank to route the water through the pipe thus leaving the
sewer crossing area dry. Perform sewer crossing construction
with downstream silt fence in place. Shape brook banks to a
387 North Main Street (203)643-2520 Manchester, CT 06040
Sediment and Erosion Control Procedures Page 2
gentle slop% seed and jute net cover to stabilize them. Backfill
temporary channel thus routing brook back into its original course.
T45*-3 (Sta 4 + 50 to Sta 13 + 33)
Install sewer through open cropland from edge of brook to edge of
Smith Street:`
Objective: Protect downhill areas and stream from siltation.caused by
construction. .
Procedure: Keep all construction and hauling activities within the designated
75' wide construction easement. Any local areas that slope
directly down to the stream (existing gullies) must be protected
by silt fence or haybales from the trenching operation. Disturb
only the minimum practical area at any one time. Finish grade
and stabilize the surface immediately following trench backfilling.
Task 4 (Sta 13 + 33 to Sta 20 + 27)
Install sewer under center of Smith Street to hook-up with Pleasant Hills
outlet.
Objective: Avoid siltation of roadside swales.
Procedure: Use normal street trenching procedures. Keep piles of excavated
material to a minimum to avoid large wash outs during rainstorms.
bT towN SEt`�
Tawn O-P S-V� ?A101�c
O � P
C U
1540 SULLIVAN AVENUE • SOUTH WINDSOR, CONN. 06074
r►osoe-CO AREA CODE 203/644-2511
' October 16, 1984
Jean Marc Jacques/The Hartman Tobacco Company
c/o Raymond G. LeFoll, Esquire
2307 Silas Deane Highway
.: Rocky Hill, Connecticut 06067 CERTIFIED MAIL
RE: APPLICATION NO. 295 - Sanitary Sewer, Property at Smith and Clark Street
Dear Attorney LeFoll:
At the October 15, 1984 meeting the South Windsor Inland Wetlands Agency
approved with conditions Application No. 295 for the purpose of constructing
an interceptor sanitary sewer under a watercourse for property located at
_. Smith and Clark Streets.
The permit is based on the amended plans entitled "Sanitary Sewer Plan"
prepared for J & R Realty of South Windsor, Connecticut, by consulting engineers
of Meehan Associates. Such _plans are dated October 15, 1984 having no revisions;
sheets 1 through 3 of 3.
M The following conditions must be adhered to for this permit to be valid:
1. Sanitary Sewer :piping under brook area will be sufficiently
reinforced concrete to the satisfaction of the Town Engineer.
2. A $25,000 Cash Bond/Letter of Credit is to be submitted prior
:..: to any construction of the proposed interceptor sanitary sewer
system at property located between Smith and Clark Streets, to
ensure its' completions within Conservation Easement only.
3. Seeding and netting is to be done on a daily basis on each
section as completed.
4. No work shall be done outside 75 ft. Conservation Easement.
5. Prior to the commencement of any site work, a meeting with
•.. Town Engineering Staff will be required.
6. The proposal is subject to the approval of the Town Engineer.
Jean Marc Jacques/ The Hartman Tobacco Company
C/o Raymond G. Le Foil, Esquire
2307 Silas Deane Highway
Rocky Hill, Connecticut 06067
Letter of Permit Application No. 295
October 16, 1984
Page 2
7. The application shall indemnify and hold harmless the Town
of South Windsor against- any liability which might- result
from the proposed operation or use.
8. The permit is valid for one year and shall expire October
15, 1985, if not initiated and compItte'd within one year
from the date of approval.
Very Truly yours,
Calvin Lane, Vice Chairman
INLAND WETLANDS AGENCY
TOWN OF SOUTH WINDSOR
CL: se
cc: Jean Marc Jacques
Richard Meehan, Meehan Associates
A.B. Davies, Deputy Town Engineer
Jacqueline Smith, Town Clerk
Richard Sartor, Town Manager
Richard Ryan, Deputy Mayor
Robert F. Gilligan, Chairman PZC
Thomas D'Auria, Builing Official
Peter DeMallie, Director of Planning
Kenneth Brill, Chairman EDC
Fred Shaw, Pollution Control
& R Realty of Connecticut, Inc.
658 ELLINGTON ROAD SOUTH WINDSOR, CT. 06074
(203) 282-0628 OR 644-9340
November 9 , 1984 `
To the Town of South Windsor ,
Please be advised that J & R Realty of Connecticut , Inc .
is posting a $25 ,000 .00 cash bond for the sewers at
Pleasant Hills Condominiums . This cash bond is only
temporary 6ntil a performance bond for $25 , 000 .00 can
be delivered to the town , at which time the $25 , 000 . 00
check (check 'B13) will be returned to J & R Realty of
Connecticut , Inc.
;y ji�c L' ';j-7` %.TL �.2�L rzi✓.� i_;��_ T�i=wit'���
aL
7
C, r� ,
fteceived Date
Zq�
LEFOLL F3 ROGGI
ATTORNEYS AT LAW
2307 SILAS DEANE HIGHWAY
ROCKY HILL,CONNECTICUT 06067
RAYMOND G.LEFOLL TELEPHONE
CURTIS H.ROGGI (203)563-2355
December 3, 1984
South Windsor Inland Wetlands Commission
South Windsor Town Hall
South Windsor, Connecticut 06074
RE: Return of $25,000 Bond for Sewer Installation
Dear Commissioners:
Please be advised that this office represents J & R Realty of Connecticut
Inc. owner and developer of Pleasant Hills Condominiums which has posted a
$25,000 Cash Bond to cover the installation of a sewer line through the
Hartman Tobacco Company land located on the easterly side of Clark Street
and the northerly side of Smith Street in South Windsor, Connecticut.
It is my understanding that this sewer installation has now been completed
and J & R Realty of Connecticut Inc. herein requests the return of its
$25,000 cash bond.
Thank you for your anticipated cooperation.
Very r y yours,
G. e o
GL/3md
TO: PLANNING AND ZONING COMMISSION
FROM: INLAND WETLANDS AGENCY
RE: J & R Realty
JMJ - Smith and Clark Streets
Application No. 295
$25►000 Cash Bond
Please .be advised that at the December 17, 1984 meeting of the
Inland Wetland Agency it was agreed upon to release, the cash
bond for Application No. 295 - J & R Realty.
Constance E'riksson, Chairman
Conservation Commission
Town of South Windsor